--- title: 'What a System Impact Assessment actually evaluates' description: 'What an IESO System Impact Assessment evaluates, who performs it, where the transmitter customer impact assessment sits, and what to look for in one.' # publishDate is the drafting date. Set it on approval (D9). publishDate: 2026-08-31 topics: ['technical-explainer'] practiceAreas: ['energy', 'technology'] readingTime: 8 draft: true reviewedByPouya: false --- ## An SIA is not an assessment of the project A connection date is a common term in Ontario energy contracts: EPC schedules, equipment supply terms, the covenants around a commercial operation date. When it moves, the System Impact Assessment is the document the argument turns to, and it invites one specific misreading. An SIA does not assess the project; it assesses what happens to the grid if the project connects to it. The term is the Independent Electricity System Operator's own, and so is its companion. In the IESO's description of the connection process, "New connections or modifications to facilities connected to a transmitter's system are subject to the IESO's system impact assessment (SIA) and the transmitter's customer impact assessment (CIA)." Two documents, two authors. The IESO conducts the SIA. The transmitter conducts the CIA. Treating the pair as one exhibit loses the distinction most of these disputes turn on. Both sit in the IESO's and transmitter's connection assessment and approval process, CAA in the IESO's usage, and each application is given a unique CAA ID. ## What the assessment is actually of The IESO describes its study step as assessing "the impact of [the] proposed new or modified connection on the reliability of the integrated power system". Stage one of the same process puts it more broadly: planned connections and modifications "must be assessed to identify and mitigate any potential adverse effect on the reliability of the electricity grid and its existing customers". The subject of the assessment is the system, not the applicant. The IESO describes its own function as coordinator and integrator of Ontario's electricity system, balancing supply against provincial demand in real time and directing the flow across the transmission lines, and it names five pillars of reliability it is responsible for meeting: capacity, energy, transmission, operability and ancillary services. An SIA asks whether a new connection disturbs those. That is also how to read a condition: the assessment's subject is the system, so a condition speaks to how the system behaves with the facility on it. The published process does not describe what conditions a report may carry — that question is answered in the report. A pleading that reads a condition as an admission of defective work is reading the document as though the other side had commissioned it. The IESO's connection-process FAQ names the tools: "The IESO uses DSA and PSSE tools to conduct SIA studies." Naming the tools is not describing the study, and the published process description does not say what a given study assumed, modelled or tested. Where the argument is about the study itself, the report and the record behind it are what answer it — not this outline of the process that produced it. ## Where it sits, and how long it takes The IESO runs connection in up to six stages: prepare application; obtain conditional approval to connect; design and build; authorize market and program participation; register equipment; commission equipment and validate performance. The SIA and the CIA both live in stage two, which "typically takes one year" on the IESO's figure. Stage four typically takes about a month, stage five at least three months, and the whole process "can take anywhere from a few months for small modifications to existing facilities, to more than three years for major modifications or to connect new facilities". All applicable stages have to be completed before final approval to connect and the start of commercial operation. Which stages apply depends on what the facility connects to: "New or modified connections to a transmitter's system are generally subject to all six stages, while new or modified connections to a distributor's system may only be subject to the first three." That last point is about parties as much as engineering. Distribution connections run through the distributor's own assessment process, and the IESO records that a distributor may itself need to participate in the IESO's and the transmitter's processes on the applicant's behalf. The entity handling the assessment correspondence is not always the entity whose contract is in dispute. ## Two documents, two authors, two agreements The sequence is where the SIA and the CIA come apart. On the IESO's account of stage two, a pre-application meeting comes first. The IESO then determines whether the application qualifies for a system impact assessment or an expedited system impact assessment (ESIA). Once the application and its deposit are in, it prepares an SIA agreement, "in accordance with section 6.1.15.3 of chapter 0.4 of the Market Rules", for execution by the applicant's authorized representative. Once all required information has been provided, it carries out the studies and issues a draft SIA report to the applicant and the transmitter for review and comments. After addressing the comments on the draft or on a revised draft, it sends the final report to both, with either a "Notification of conditional approval (NoCA)" or a "Notification of disapproval with reasons (NoDR)". The CIA runs on a different clock. The transmitter "generally initiates the customer impact assessment (CIA) after the draft SIA report from the IESO", and the CIA has its own agreement, between the applicant and the transmitter. Three consequences follow. The assessments are generally sequenced rather than parallel, so a slipped draft SIA ordinarily pushes the CIA start behind it. There are two contracts before there are two reports, and the obligations parties argue about, which information was owed and by when, live in those two agreements. And the draft-and-comment step is a record: what a party said about a study assumption at draft stage, and what it declined to say, sits in that record alongside the final report. ## What to ask for, and what the record will not support Where a dispute turns on an SIA, the productive order is the order in which the record was made, not the order of the pleadings. The application first, and the IESO's FAQ names the instrument: Form 128 initiates the SIA process. Then the two agreements. Then the information the applicant supplied, with dates, because the study step begins once all required information has been provided: completeness is the hinge on which a year-long stage moves. Then the draft SIA report and each set of comments on it. Then any revised draft. Then the final report with the NoCA or the NoDR. Then the CIA. The final report may already be public: the IESO states that it "will be published on the IESO website in the Application Status table at the end of the month in which it was finalized". Upstream of all this sits an optional technical feasibility study, a "confidential service" provided "on a cost-recovery basis to identify and mitigate potential issues with various connection options"; whether one was run often explains why a particular option was chosen. Two arguments the published process will not carry. First, the queue. Ontario has no interconnection queue. The IESO is explicit: it "is not using an 'interconnection queue'", adopting instead "the concept of 'committed projects' that is defined in Section 3.3 of Market Manual 1.4: Connection Assessment and Approval", and there is "no option to 'skip the interconnection queue'". Each assessment follows the timelines in section 5.8 of that manual. A head of loss framed as a lost place in a queue rests on a mechanism the system operator says it does not operate. Second, differential treatment. Renewable generation is not assessed differently: "The treatment of new renewable generation facilities is no different than any other new facility, the normal System Impact Assessment (SIA) process applies to the connection of all generation facilities, renewable or non-renewable, equally." A delay theory resting on technology-specific handling has nothing in the published process to stand on. ## Why more contracts are about to depend on this As this is written in August 2026, the gate in front of large loads is being rebuilt around the assessment, not in place of it. Section 28.1 of the Electricity Act, 1998 came into force on 11 December 2025. Unless a transmitter or distributor is satisfied that the "specified connection requirements" have been complied with, it "shall not" connect or reconnect a "specified load facility". That category is defined to include a data centre meeting criteria that may be set out in the regulations, and a facility whose demand at the point of connection exceeds a prescribed amount. The section arrived through Bill 40 of the 44th Parliament, 1st Session — the Protect Ontario by Securing Affordable Energy for Generations Act, 2025 — which received Royal Assent on 11 December 2025 as chapter 22 of the Statutes of Ontario, 2025. Its transition rule turns on a date and a form: the section does not apply where a connection request made in accordance with the Transmission System Code or the Distribution System Code was submitted to the transmitter or distributor before 3 June 2025, the day Bill 40 had First Reading. The regulation that would fill in those criteria is the part to watch. The Ministry of Energy and Mines' August 2026 consultation on an economic and strategic assessment framework for new data centres describes the province as "considering drafting" a regulation that would require new large data centres to obtain government approval to connect or reconnect. Its comment period runs to 12 September 2026, and the same notice carries the Ministry's estimate that data-centre connection proposals could total more than 10,000 MW cumulatively. None of that displaces the SIA; it sits on top of it. A large load will still be assessed for its effect on the reliability of the integrated power system, in stage two, and its transmitter will still run a CIA. What changes is the number of contracts written against a connection date whose gating conditions were still under consideration as at August 2026. ## Reading the study and the contract on the same page Grid connection disputes are argued through technical studies. I work as a machine-learning and DevOps infrastructure engineer. The study assumptions, the modelling inputs and the constraint that produced a condition are documents I read directly and work through with the parties. In a [mediation](/mediation/) that means a technical disagreement can be tested in the room rather than deferred to an expert exchange. In a [commercial arbitration](/arbitration/) it means the first procedural order can be built around the documents that decide the matter. [The shape of an engagement](/process/) sets out where each one starts. Connection is one of the areas I take appointments in, set out at [energy and grid disputes](/practice/energy/); its large-load half overlaps with [technology and data disputes](/practice/technology/). Every date above is as at August 2026, and the instruments move. Nothing here is applied to a particular matter, and each party to a dispute should have their own legal advice.